This paper presents the analysis of main technical deficiencies of nuclear power plants (NPPs) in preparedness for safe long term operation (LTO) and the main corrective measures in an early phase of preparation for safe LTO of NPPs. It focuses on technical aspects connected with management of physical ageing of NPP structures, systems and components (SSCs). It uses as a basis results of IAEA SALTO missions performed between 2005 and 2016 (see also paper NED8805 in Nuclear Engineering and Design in May 2016) and the personal experiences of the authors with preparation of NPPs for safe LTO. This paper does not discuss other important aspects of safe LTO of NPPs, e.g. national nuclear energy policies, compliance of NPPs with the latest international requirements on design, obsolescence, environmental impact and economic aspects of LTO. Chapter 1 provides a brief introduction of the current status of the NPP’ fleet in connection with LTO. Chapter 2 provides an overview of SALTO peer review service results with a focus on deficiencies related to physical ageing of safety SSCs and a demonstration that SSCs will perform their safety function during the intended period of LTO. Chapter 3 discusses the main corrective measures which NPPs typically face during the preparation for demonstration of safe LTO. Chapter 4 summarizes the current status of the NPP’ fleet in connection with LTO and outlines further steps needed in preparation for safe LTO.

English abstract

This paper presents the analysis of main technical deficiencies of nuclear power plants (NPPs) in preparedness for safe long term operation (LTO) and the main corrective measures in an early phase of preparation for safe LTO of NPPs. It focuses on technical aspects connected with management of physical ageing of NPP structures, systems and components (SSCs). It uses as a basis results of IAEA SALTO missions performed between 2005 and 2016 (see also paper NED8805 in Nuclear Engineering and Design in May 2016) and the personal experiences of the authors with preparation of NPPs for safe LTO. This paper does not discuss other important aspects of safe LTO of NPPs, e.g. national nuclear energy policies, compliance of NPPs with the latest international requirements on design, obsolescence, environmental impact and economic aspects of LTO. Chapter 1 provides a brief introduction of the current status of the NPP’ fleet in connection with LTO. Chapter 2 provides an overview of SALTO peer review service results with a focus on deficiencies related to physical ageing of safety SSCs and a demonstration that SSCs will perform their safety function during the intended period of LTO. Chapter 3 discusses the main corrective measures which NPPs typically face during the preparation for demonstration of safe LTO. Chapter 4 summarizes the current status of the NPP’ fleet in connection with LTO and outlines further steps needed in preparation for safe LTO.

Keywords in English

Ageing management, Long term operation, Nuclear power plant, Structures, Components, Nuclear safety

Released

01.05.2017

Publisher

Elsevier

ISSN

0029-5493

Volume

2017

Number

316

Pages from–to

125–130

Pages count

6

BIBTEX


@article{BUT138890,
  author="Robert {Křivánek} and Jan {Fiedler},
  title="Main corrective measures in an early phase of nuclear power plants’ preparation for safe long term operation",
  year="2017",
  volume="2017",
  number="316",
  month="May",
  pages="125--130",
  publisher="Elsevier",
  issn="0029-5493"
}